Project description

Council is completing road safety upgrades on Fieldstone Boulevard from Beaconsfield-Emerald Rd to Holm Park Rd.   

This project is part of the Australian Government’s 2024 – 2025 Black Spot Program and Council’s Local Area Traffic Improvement program. 

Works will include: 

  • The installation of three new flat top road humps between Scenic Dr and Harbour St 
  • The installation of two pairs of asphalt speed cushions to the east of Timberside Dr, between Northview Ct and Gumview Blvd 
  • Kerb and channel realignment work 
  • Minor concrete footpath work 
  • Lighting upgrades at 6 locations 

In mid-2023, Council completed community consultation regarding the installation of local area traffic management devices/speed humps, otherwise referred to as speed humps.  

This consultation was prompted by a review of road safety in the area, which identified significant risk due to the number of reported crashes, customer requests and the traffic and speed data. 

 

 

Funding

This project is funded through: 

  • the Australian Government’s 2024 – 2025 Black Spot Program 
  • Cardinia Shire Council’s Local Area Traffic Improvement program. 

Progress update

Road safety upgrades are now underway along Fieldstone Blvd between Beaconsfield-Emerald Rd to Holm Park Rd.  

Stage 1 works (February – March 2025): 

  • Lighting upgrades from Beaconsfield-Emerald Rd to Holm Park Rd. 

Stage 2 works (May – June 2025): 

  • New flat top road humps 
  • Asphalt speed cushions 
  • Kerb and channel realignment 
  • Minor footpath work 
Construction construction-icon
Project Highlights
  • From 21 February, road safety upgrades will be underway on Fieldstone Boulevard from Beaconsfield-Emerald Rd to Holm Park Rd.   
  • Works are expected to be completed by June 2025, conditions permitting.