Project description

Level crossing removals – Beaconsfield

The Victorian Government has removed the level crossing at Station Street in Beaconsfield by building a new road bridge over the rail line.

The road bridge design was quicker to build and less disruptive for motorists and rail passengers, as the majority of the works were able to be built offline.

The removal of the Station Street level crossing will improve safety and reduce congestion for local residents, and allow for more trains to run more often on the Pakenham line.

Works are still underway to remove the signalling infrastructure, build the shared user paths and finish landscaping around the station.

Visit Victoria’s Big Build project pages to view further information including:

  • info about each project
  • current works notices and disruptions
  • how to sign up for email updates
  • engagement opportunities
  • contact information if you have questions about a project
  • image galleries

Brunt Road Beaconsfield   Station Street Beaconsfield

Enquiries and updates

 

Funding

This is an external project being funded and delivered by the Victorian Government’s Big Build project.

 

Progress update

From Monday 24 March, LXRP opened the new road bridge and permanently closed the Station Street level crossing.

In 2024, LXRP, in collaboration with Council, Geographic Naming Victoria (GNV), Beaconsfield Progress Association (BPA), and the community, conducted a consultation to name the new road bridge.

After a community vote, McKenna Drive was chosen to honour Carmel McKenna for her significant contributions to the Beaconsfield community.

For more information on the project, visit Victoria’s Big Build website.

Current Status: Construction construction-icon
Project Highlights
  • Station Street, Beaconsfield level crossing to be removed by 2025