Sealing the Hills is a vital infrastructure program which aims to upgrade currently unsealed roads in the Dandenong Ranges and surrounding townships.

 

Unsealed roads are heavily impacted by weather conditions, land formations and increased traffic, particularly in the Dandenong Ranges. 

 

Upgrading these unsealed roads will improve community safety, access to community facilities and amenities and the connectivity of the existing road network, while reducing dust, pollution and maintenance issues. 

 

Project description

Upgrade sealing works are being completed on Blackwood Lane, Gembrook Road (service road), Redwood Road (service road unsealed section) and Russell Road, Gembrook.

Works include:

  • feature pavement construction
  • kerb channel construction
  • construction of traffic calming devices
  • drainage improvement works
  • signage
  • line-marking

 

Funding

This project is jointly funded by the Australian Government and contributions by residents via a Special Charge Scheme.

 

Progress update

Asphalt works are complete on Russell Road, Gembrook Road Service Road, Blackwood Lane, and Redwood Road.

The contractor for these works was MACA.

Have your say on the Russell-Blackwood package

Completed completed-icon
Project Highlights
  • Works are complete on Russell Road, Gembrook Road Service Road, Blackwood Lane, and Redwood Road.