Project description
We’re working to seal Mount Burnett Road in Mount Burnett.
Upcoming works include:
- Road pavement construction
- Spray sealing the remaining unsealed 1.9km length of road
- Drainage works
- Signage
- Line marking
- Minimal tree removal
As part of the Mount Burnett sealing project, some minor tree removal is expected to ensure safe and efficient road works.
We’re committed to minimising environmental impact and will keep the community informed as the project progresses.
Council understands the community’s concerns about the current 100 km/h speed limit on Mount Burnett, and for more on how to request a speed limit change or review, please read our frequently asked questions.
Funding
This project is funded by:
- Australian Government
- Cardinia Shire Council
Progress update
Construction is now underway on Mount Burnett Rd.
Works are expected to be completed by June 2026, conditions permitting.
Sure Constructions has been appointed as the contractor.
What to expect during works:
- Traffic management in place
- Reduced speed limits
- Temporary road closure. Access to be maintained to all properties and local traffic
- Detours will be signed to redirect traffic
Review the design plans for Mt Burnett Rd
Information session – November 2025
Thank you to everyone who attended the community information session on 11 November 2025 regarding the planned sealing works for Mt Burnett Road.
We appreciated the opportunity to share details about the construction plans and schedule, and to answer your questions. Your input and support is valuable in helping us deliver this project successfully.
For more information on speed limits changes, please read our frequently asked questions.
If you were unable to attend or would like to revisit the information, please get in touch with us.
We look forward to working with the community as the project progresses and will continue to keep you informed.
Project Highlights
- Upgrade works underway from February – June 2026.
- Contractor appointed in December 2025.
- Information session was held for the community on 11 November 2025
- Works are progressing, with drainage works and road pavement construction underway. On track for completion in May 2026
Pictures