Sealing the Hills is a vital infrastructure program which aims to upgrade currently unsealed roads in the Dandenong Ranges and surrounding townships.
Unsealed roads are heavily impacted by weather conditions, land formations and increased traffic, particularly in the Dandenong Ranges.
Upgrading these unsealed roads will improve community safety, access to community facilities and amenities and the connectivity of the existing road network, while reducing dust, pollution and maintenance issues.
Project description
Upgrade sealing works on stage 2 of the First-Grenville package are scheduled to start in late 2023.
Stage 2 works will take place on Second Avenue, Cockatoo.
Stage 1 works will take place on First Avenue, Grenville Road, Spring Street, Hazel Street and the ROWY, Cockatoo.
Stage 3 works will take place on Neville Street, Steane Street and Marcelle Street, Cockatoo.
Works include:
- feature pavement construction
- kerb channel construction
- construction of traffic calming devices
- drainage improvement works
- signage
- line-marking
Funding
This project is jointly funded by the Australian Government and contributions by residents via a Special Charge Scheme.
Progress update
Upgrade sealing works on Second Avenue is underway.
The contractor for these works is Sure Constructions.
Have your say on the First-Grenville package
Updates
- Drainage works have started with pavement works to follow.
Project Highlights
- Works are underway and are expected to be completed by late 2024