• Loading...
  • 0 results found, please refine or try another search

The Koo Wee Rup Bowling and Community Hub will replace the existing pavilion located at the south end of the reserve, which was built in the late 1960s.

 

The pavilion is used regularly by Koo Wee Rup Bowling Club and Southwest Gippsland Midweek Bowls Group. It is also used on occasion by Koo Wee Rup Lions Club and other community and private groups.

 

The new pavilion will better support the current clubs, as well as other local sporting clubs, schools and community groups that host meetings and functions.

Project description

The existing clubroom facility is being demolished and will be reconstructed with facilities for club members and the general community.

The new clubroom will feature two social rooms, a bistro area, three community meeting rooms, a kitchen, bar servery, two change room areas, an office area, toilet facilities, storage area, a first aid room, a covered spectator area and car parking.

Previous community consultation was completed in 2021 and 2022 for Koo Wee Rup Bowling Club and Community Hub pavilion project.

View previous Have Your Say for the Koo Wee Rup Bowling Club project

Funding

This project is jointly funded by Council, Victorian and Australian Government agencies.

Progress update

The construction tender for design and construction closed on 4 August 2023. Tender assessment is completed.

Revised delivery timing for this project is November 2024.

 

Tender tender-icon
Project Highlights
  • Revised delivery for this project is November 2024