Sealing the Hills is a vital infrastructure program which aims to upgrade currently unsealed roads in the Dandenong Ranges and surrounding townships.
Unsealed roads are heavily impacted by weather conditions, land formations and increased traffic, particularly in the Dandenong Ranges.
Upgrading these unsealed roads will improve community safety, access to community facilities and amenities and the connectivity of the existing road network, while reducing dust, pollution and maintenance issues.
Project description
Upgrade sealing works on stage 3 of the First-Grenville package are expected to start in early 2024.
Stage 3 works will take place on Neville Street, Steane Street and Marcelle Street, Cockatoo.
Works include:
- feature pavement construction
- kerb channel construction
- construction of traffic calming devices
- drainage improvement works
- signage
- line-marking
Other stages
Stage 2 works will take place on Second Avenue, Cockatoo.
Stage 1 works will take place on First Avenue, Grenville Road, Spring Street, Hazel Street and the ROWY, Cockatoo.
Funding
This project is jointly funded by the Australian Government and contributions by residents via a Special Charge Scheme.
Progress update
Upgrade sealing works on Neville Street, Steane Street and Marcelle Street are underway and expected to be completed by late 2024.
The contractor for these works is Sure Constructions.
Have your say on the First-Grenville package
Updates
- Drainage, stabilisation, kerb and base layer works complete on Neville Street.
- Drainage works commenced on Marcelle and Steane Streets with stabilisation to proceed in the next month.
Project Highlights
- Works are underway and are expected to be completed by late 2024