Sealing the Hills is a vital infrastructure program which aims to upgrade currently unsealed roads in the Dandenong Ranges and surrounding townships.

 

Unsealed roads are heavily impacted by weather conditions, land formations and increased traffic, particularly in the Dandenong Ranges. 

 

Upgrading these unsealed roads will improve community safety, access to community facilities and amenities and the connectivity of the existing road network, while reducing dust, pollution and maintenance issues. 

 

Project description

Roadworks on Durban Road, Old Gembrook Road and Sherriff Road, Emerald is underway.

Works will include:

  • feature pavement construction
  • kerb channel construction
  • construction of traffic calming devices
  • drainage improvement works
  • signage
  • line-marking

 

 

Funding

This project is jointly funded by the Australian Government and contributions by residents via a Special Charge Scheme.

 

Progress update

Upgrade sealing works are progressing on Durban Road, Old Gembrook Road and Sherriff Road, Emerald.

Council has engaged A1 Civil to undertake upgrade works on its behalf.

Construction is on track and expected to be completed by the end of December 2025, conditions permitting.

Read our media release on the construction start

Ongoing works

  • Kerb and channel
  • Stabilisation
  • Pavement works

 

Minor rectification works 

As part of finalising all works completed as part of the Sealing the Hills program, minor rectification works are scheduled to be completed from 11 May to July 2026 conditions permitting, 

Works will vary, and may include: 

  • Drainage improvements 
  • Signage improvements 
  • Minor roadside works
     

What to expect

During construction, temporary disruptions may include:  

  • Increased noise, dust and lighting 
  • Increased traffic on surrounding streets 
  • Traffic management including reduced speed limit will be in place. 

Access will be maintained to all properties during construction, and we will be working to minimise disruptions where possible.

Current Status: Construction construction-icon
Project Highlights
  • Works started in early July 2025
  • Minor rectification works are underway and are expected to be completed by July 2026, conditions permitting.